Community Discussion

Planning Decision – 12/09/2024 – ABP Decided to Grant Permission for the Proposed Wind Farm

Planning Decision Due – 19/08/2024 – ABP failed to achieve decision deadline

Planning Decision Due – 21/06/2024 – ABP Delayed until the 19th August 2024

Planning Application – 15/12/2023 – Lodged to An Bord Pleanála – ABP Ref: PA92.318704

June 2021

Enerco Energy Brochure

Site Location Map

Site Context Map – OSI

Site Context Map – Aerial

Letter to Residents

August 2022

Letter to Residents

Biodiversity Brochure

March 2023

Letter to Residents

Turbine Layout Map

May 2023

Letter to Residents

Newspaper Advertisement

Public Information Exhibition – June 2023

September 2023

Letter to Residents

Newspaper Advertisement

Public Information Exhibition – October 2023

Additional Information

Additional Photomontages